SolarEdge SE5K Installation Manual page 46

Three phase system with setapp configuration for europe and apac
Hide thumbs Also See for SE5K:
Table of Contents

Advertisement

Chapter 5: Activating, Commissioning and Configuring the System Using the
Inverter Energy
Today
45 kWh
Total: 41.03 MWh
Today: since midnight
This Month: since 1st of the current month
This Year: since January 1st
Total (Wh): The inverter total energy. If an external meter is installed, the value
displayed in this line depends on the meter type connected to the inverter and
its location:
If a bidirectional meter is connected at the consumption point, this
value is the consumed energy.
If the meter is installed at the production point, this value is the energy
produced by the site.
If the meter is installed at the grid connection point, this value is the
energy exported to the grid.
Meter Status
Export – RS485-2 Modbus ID #2
Three Phase System Installation Guide MAN-01-00505-1.2
This Month
This Year
1.14 MWh
13.68 MWh
 
 
Meters
Status: OK
Inverter SetApp
    45