Electrical - Worcester Greenstar i Series Installation, Commissioning And Servicing Instructions

Wall hung rsf gas fired condensing system boiler for sealed central heating systems and indirectly fed domestic hot water
Table of Contents

Advertisement

2.
Fig. 49 Fitting syphon
NOTICE: Do not use solvents, adhesive or lubricant
when pushing the pipe onto the rubber connector.
3. Push the discharge hose, onto the condensate outlet pipe.
Maintenance
Fig. 50
There is no need to remove the Syphon Assembly for cleaning.
To drain debris from the syphon, during the annual service:
▶ Release the clips and remove the drainage cap from the bottom of the
syphon.
▶ Empty the debris and condensate from the syphon into a suitable
container.
▶ Re-fit the drainage cap to bottom of the syphon.
4.7

ELECTRICAL

CAUTION: ISOLATE THE MAINS ELECTRICITY SUPPLY
BEFORE STARTING ANY WORK AND OBSERVE ALL
RELEVANT SAFETY PRECAUTIONS.
The boiler is pre-wired with a two metre mains supply
cable.
A spare strain relief block is supplied in case the pre-
wired cable is not used.
• The mains electrical supply to the boiler must be through either a
fused double pole isolator or a fused three pin plug and unswitched
socket.
• The isolator shall be situated next to the boiler for new systems and,
where practicable, replacement boilers.
• The isolator must have a contact separation of 3mm minimum in both
poles. Any system connected to the boiler must not have a separate
electrical supply.
• External fuse rating 3A.
6 720 804 532 (2012/09)
1.
6720644743-13.2Wo
1
6720644743-14.1Wo
ACCESS TO ELECTRICAL CONNECTIONS:
▶ Remove boiler casing to access control panel.
1. Refer to figure 51 and remove the screw securing the control panel.
2. Lower the control panel into the horizontal service position.
1.
2.
Fig. 51 Moving control panel into the service position
When stripping wires always ensure copper strands do
not fall into the control box.
1. Refer to figure 52 and unscrew the three screws in the control panel.
2. Pull off the connections cover.
1.
Fig. 52 Removing the connection cover (SMPS)
▶ Pass the 230 V mains power cable, from the control box, through the
grommet at the right hand side of the pre-plumbing manifold and
route to the mains isolator next to the boiler.
SI1
Fuse F1 2.5A
ST6
Frost thermostat connection
ST10
Mains in & external controls connections
ST18
Code plug
ST10
S11
ST18
Fig. 53 Electrical connector information
INSTALLATION
6720644743-18.1Wo
1.
2.
1.
ST6
27

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Greenstar 24iGreenstar 12iGreenstar 15iGreenstar 18i

Table of Contents