Condensate Pipe Work - Worcester Greenstar i Series Installation, Commissioning And Servicing Instructions

Wall hung rsf gas fired condensing system boiler for sealed central heating systems and indirectly fed domestic hot water
Table of Contents

Advertisement

1
3
Fig. 5 Additional expansion vessel
1
Appliance expansion vessel - CH
2
Extra expansion vessel - CH return
3
Pressure relief discharge
Table 7 Key to fig. 5
EXISTING BUILDS: S AND Y PLAN SYSTEMS:
NOTICE: The boiler is fitted with its own internal bypass.
1
Diverter/Zone valve
2
Radiator valve (flow)
3
Lock shield valve (return)
4
Bypass
S PLAN LAYOUT
M
4
Fig. 6 Existing build - S Plan
Y PLAN LAYOUT WITH EXTERNAL DIVERTER VALVE
1
M
Fig. 7 Existing build - Y Plan external diverter valve
NOTICE:
▶ A drain cock should be fitted at the lowest point of the
heating circuit and beneath the appliance.
6 720 804 532 (2012/09)
2
3
2
1
6720644743-05.1Wo
3
2
6720644743-06.1Wo
OPTIONAL DIVERTER VALVE
This boiler is designed to operate on a sealed system only. The boiler will
require a second return pipe from the water cylinder to the wall
mounting frame and terminate in 15mm copper pipe.
EXISTING BUILD - SYSTEM LAYOUT WITH OPTIONAL INTERNAL
DIVERTER VALVE (NOT SUPPLIED WITH BOILER)
Boiler flow
Cylinder return
Heating return
Fig. 8 Existing build - Internal diverter valve
NEW BUILD - TWO ZONED HEATING SYSTEM
The latest Part L1a regulation for new installations require separate zone
controls for the central heating.
1
4
Fig. 9 New build - System layout
3.4

CONDENSATE PIPE WORK

NOTICE:
▶ Where a new or replacement boiler is being installed,
access to an internal "gravity discharge" point should
be one of the factors considered in determining boiler
location.
▶ The condensate pipe must be nominally
22mm Ø plastic pipe.
▶ The condensate pipe work must fall at least 52mm per
metre towards the outlet and should take the shortest
practicable route.
▶ Ensure there are no blockages in the pipe run.
Key to condensate illustrations
1
Condensate discharge from boiler
2
Soil and vent stack
3
Minimum 450mm and up to three storeys
4
Visible air break at plug hole
5
Sink or basin with integrated overflow
6
75mm sink waste trap
7
Condensate pump
*
Condensate trap of 75mm already incorporated into the boiler
PRE-INSTALLATION
3
2
6720644743-07.1Wo
3
2
6720644743-42.1Wo