Preparation for start-up, start of operation

Check before first start-up of unit
General functions and check
whether all components of air handling device are
in place and properly connected
whether the cooling and heating circuits are
connected and whether the supplies are accessible
whether all electric appliances are accessible
whether all condensate drain kits are installed
whether all elements of measuring and control are
installed
Electric installation
according to schemes of wiring check whether all
electric elements of unit are correctlly connected
Fan section
check the fan impeller for intactness and free
rotation.
check the tightening of the Taper-Lock collets.
check the tightening of the screw joints of the fan
assembly.
Filter section
state of filters
attachment of filters
setting of pressure difference sensors
Water heater section
state of heat transmission surface
state of inlet and outlet duct connection
state and connection of mixing set
state, wiring and installation of elements
of anti-freeze protection
Electric heater section
state of heating coils
connection of heating coils
connection of safety and operating thermostats
Water cooler and direct evaporator section
state of heat transmission surface
state of inlet and outlet duct connection
connection of condensate drain kit
elements and connection of cooling circuit
state of drop eliminator
Plate heat exchanger section
state of heat exchanger vanes
functionality of bypass damper
state of drop eliminator
connection of condensate drain kit

Putting device in operation

Only a person with necessary qualification may put the
unit in operation. Before the first start a qualified worker
must perform a revision of electric installation of all con-
nected components of air handling device.
Safety precautions
Sections with accident risk (by electric current,
rotating elements etc.) or with connecting points (inlet
- outlet of heating water, air flow direction etc.) have
always warning or informative label.
It is prohibited to operate unit fans when the door
is opened or when the panels are removed. Service
panels must be during operation always closed.
10
Air handling units
Before work on fan part is started, make sure that the
main switch is off and make such moves which will pre-
vent unintentional switching of the motor during mainte-
nance.
When emptying the exchanger the water temperature
must be lower than 60°C. Temperature of connecting
piping must also be lower than 60°C.
Removal of life electric heater service panel is prohi-
bited and changing production setting of safety thermo-
stat is prohibited as well.
Operate electric heater without outlet air temperature
control and without providing steady speed of air flow is
prohibited.
Putting unit in operation at not adjusted installation can
only be done with closed control damper at the inlet to
the unit. Operation of a unit at not adjusted installation
could lead to overloading the motor and to its perma-
nent damage. If second stage of filtration is part of the
unit we recommend to perform a trial operation without
inserts of second filtration degree.
Check during first start-up of unit
rightness of fan rotation direction according to an
arrow on the impeller.
current consumption of all connected devices (may
not exceed value mentioned on the label)
whether the water in the seal-pipe has not been suc-
ked off. The height of the seal-pipe must be raised
state of filter attachment
During trial operation try to notice presence of impro-
per noises and abnormal unit vibrations for at least
30 minutes. Sources must be detected and removed.
During the trial operation perform the adjustment of unit.
Before starting permanent operation we recommend to
regenerate or change filtration inserts. Detailed check
description of a device that is being put in operation is
included in the Service book for REMAK devices, where
according to guaranty requirements the first operation
of the device must be mentioned.