Protection Against Contamination When Installing Pipes; Pipe Connection - Daikin VRV-WII FXYCP30MY1 Installation Procedure

Table of Contents

Advertisement

1
Installation of outdoor
1 - 8 Refrigerant piping
1 - 8 - 2

Protection against contamination when installing pipes

Take measures to prevent foreign materials like moisture and contamination from mixing into the system.
Place
Outdoor
Indoor
Great caution is needed when passing copper tubes through walls.
1 - 8 - 3

Pipe connection

Only use the flare nuts included with the unit.
Using different flare nuts may cause the refrigerant to leak.
Be sure to perform a nitrogen blow when brazing.
(Brazing without performing nitrogen replacement or releasing nitrogen into the piping will create large quantities of oxidized film on the inside of
the pipes, adversely affecting valves and compressors in the refrigerating system and preventing normal operation.)
C
AUTION
Do not use anti-oxidants when brazing the pipe joints. Residue can clog pipes and break equipment.
N
OTES
1
For nitrogen replacement method, see the "Installation Manual" (contact your dealer).
2
The pressure regulator for the nitrogen released when doing the brazing should be set to 0.02 MPa(0.2kg/cm2) or less.
Refrigerant pipe
Location to be brazed
Nitrogen
Taping
Manual valve
Regulator
Precautions when connecting pipes
See the following table for flare part machining dimensions.
When connecting the flare nuts, apply refrigerant oil to the inside and outside of the flares and screw them in by hand three or four times at first.
(Use ester oil or ether oil.)
See the following table for tightening torque.
(Applying too much torque may cause the flares to crack.)
After all the piping has been connected, check the gas leak with nitrogen.
Pipe size
ø9.5
ø12.7
ø15.9
Not recommendable but in case of emergency
You must use a torque wrench but if you are obliged to install the unit without a torque wrench, you may follow the installation method mentioned below.
After the work is finished, make sure to check that there is no gas leak.
When you keep on tightening the flare nut with a spanner, there is a point where the tightening torque suddenly increases. From that position, further
tighten the flare nut the angle shown below:
Pipe size
ø9.5
ø12.7
ø15.9
• Installation procedure
Installation period
More than a month
Less than a month
Regardless of the period
Tightening torque (N·m)
32.7 - 39.9
49.5 - 60.3
61.8 - 75.4
Further tightening angle
60 to 90 degrees
30 to 60 degrees
30 to 60 degrees
®
• VRV
Systems • Installation procedure
A (mm)
Flare shape
12.8 - 13.2
90 ±2
16.2 - 16.6
A
19.3 - 19.7
R=0.4~0.8
Recommended arm length of tool
Approx. 200 mm
Approx. 250 mm
Approx. 300 mm
Protection method
Pinch the pipe
Pinch or tape the pipe
23