Once the pilot holes have been drilled and the lag screws have been installed as per Figure 1, lift the Base Module unit and hang the unit on the lag
screws . Tighten the screws fully to secure the unit .
For installing a TRIPLEX or QUAD package, mount the Base Module Package first . The Extension Module is designed to be installed to the left of the Base
Module Package . Place a 3" Victaulic flex coupling on the left end of the Base Module manifolds, drill pilot holes for the screw locations supporting the
Extension Module, and install the lag screws leaving approximately ¼" space between the screw head and the wall . Lift the Extension Module onto the
screws and then link the manifolds by tightening down the Vic coupling . Once the manifolds are attached, tighten down all of the lag screws .
2. Header End Cap Installation
1 . Discharge End Cap Header – This end cap piece is equipped with the bladder tank and a 1-1/4" open threaded port and is configured for
installation on the left end of the discharge header . If the end cap is to be installed on the right end, the bladder tank can be easily moved to
the open 1-1/4" port . Attach the Discharge End Cap Header to the discharge header using a 3" Victaulic flex coupling .
2 . Suction End Cap – Attach this end cap to the opposite side of the suction header from the incoming site water connection using a 3" Victaulic flex coupling .
6
Figure 2
36.13 in QUAD ONLY
25.13 in TRIPLEX ONLY
DISCHARGE HEADER
CONNECTION POINT TO
SYSTEM PIPING
(REFERENCE POINT FOR LAG
BOLT LOCATIONS)
DRILLING LOCATION
FOR LAG BOLTS
(8 FOR DUPLEX, 12 FOR
TRIPLEX, 16 FOR QUAD)
LAG BOLT PILOT HOLE DRILLING LOCATIONS
24.13 in QUAD ONLY