Section 5: Commisioning

Before commissioning, please ensure the actuator is correctly assembled and electrically
connected. (see Section 4,).
CAUTION: REMOVE SILICA GEL
Remove silica gel from the connection compartment.
5.1

General

CAUTION: RESET ELECTRIC END POSITIONS
During commissioning and after every disassembly of the actuator, the electric end posi-
tions (see Section 5.4) must be reset.
5.2

Manual Operation

The use of a differential gearbox in the handwheel assembly makes mechanical switching
unnecessary during manual operation.
CAUTION: DO NOT USE CHEATER BARS
Manual operation with mechanical or electromechanical equipment (such as: lever, drilling
machine, etc.) is NOT ALLOWED, as this may damage the product.
5.3

Mechanical Default Settings and Preparation

The use of linear sensors makes mechanical settings unnecessary.
CAUTION: ADJUST TORQUE BEFORE OPERATION
Before the motorised operation of the valve, it is essential to check and eventually adjust
torque settings.
5.4

End Limit Setting

A detailed description of the operation of the RTS Compact Linear CL controller can be
found in Section 6.3.
Commissioning
Section 5: Commissioning
February 2019
18