The engineering supervisor should have received corresponding ZTE training and ob-
tained certification.
l
The engineering supervisor should be familiar with the materials, tools and operation
methods used in the installation.
l
The engineering supervisor should be familiar with the installation flow and installation
methods of each component.
l
The engineering supervisor should follow the "Safety First" principle, to ensure the
smooth completion of installation.
Requirements to Installation Personnel
l
The installation personnel should have received corresponding ZTE training and
obtained certification.
l
The installation personnel should be healthy, have not drunk alcohol.
l
The installation personnel should follow the safety instructions of tools, and use safety
belts.
l
The installation personnel should fasten the tools, to prevent them from falling.
l
The installation personnel should not wear loose clothes and slippery shoes.

4.2.3 Technical Document Preparation

Before installing R8860E GU858, make sure that the following technical document is at
hand:
l
ZXSDR R8860E GU858 GU858 Outdoor GSM&UMTS Dual Mode Macro RRU User
Manual
4.2.4 Tools and Instruments Preparation
Table 4-2
Table 4-2 Tool and Meter List
Cate-
gory
Special-
purpose
tools
SJ-20101210110401-001|2010-12-06
shows tools and meters list required during installation.
Name
One feeder connector knife
One 75 Ω coaxial cable stripper
4-9
ZTE Proprietary and Confidential
Chapter 4 Installation
Example