10 Tests
NOTE: All tests require login at Service level.
10.1 Testing the wirings
All cables are tested simultaneously.
The test shows whether the sensors with their connections are correct.
NOTE: Wiring test is active until it is set to Passive. For the control to work, the cable test in normal operation
must be set to Passive.
1. From the Main index select Commissioning.
2. Select Wiring test.
3. Set Wiring test in Active mode, press OK.
4. Read the test results by selecting
Heating Circuit 1 or Domest. hot water.
5. The cables were OK and this is indicated by the
three OKs in the image opposite.
6. Wiring test is to be set to Passive after the test.