Commissioning Checklist; Re-Commissioning; Requirements; Start-Up - Daikin Altherma 3 ECH2O Installation And Maintenance Instructions Manual

Table of Contents

Advertisement

5

Start-up

5.1.6

Commissioning checklist

Commissioning checklist/Check off measures carried out
1.
Supply indoor unit and outdoor unit (if present) with voltage
2.
Enter "Expert code"
3.
Set the operating parameters
[→ Configuration Wizard → Setting parameters]
[Hot water temperature target 1]
▪ Do not set below 40 °C during commissioning.
▪ Never set below 35 °C after commissioning!
4.
Activate the ventilation function
▪ Check the water pressure
▪ Checking the minimum flow
5.
Activate the "Heating" operating mode
Observe the waiting time (up to 5 min)
▪ For outside temperatures below -2 °C and a storage temperature below
30 °C
▪ For outside temperatures below 12 °C and a storage tank temperature below
23 °C
▪ In this case, the storage tank is heated with the help of the backup heater.
6.
Commissioning is complete when a DHW temperature
40 °C appears on the display.
7.
[Screed drying] (if necessary)
Screed drying only after commissioning is complete. As soon as the temperat-
ure of the storage tank is at least 40 °C, activate (also possible without outdoor
unit).
5.2

Re-commissioning

5.2.1

Requirements

CAUTION
Commissioning in frosty conditions can result in damage to
the entire heating system.
▪ Commissioning at temperatures below 0 °C only if a wa-
ter temperature of at least 5 °C is guaranteed in the
heating system and the storage tank.
▪ We recommend not to operate the installation in ex-
tremely frosty conditions.
▪ The indoor unit is fully connected.
▪ The refrigerant system is dehumidified and filled with the specified
amount of refrigerant.
▪ The heating and hot water system has been filled and pressurised
to the correct pressure
(see Chap.
▪ The storage tank is filled up to the overflow
Installation and maintenance instructions
32
7.2.2).
(see Chap.
7.2.1).
These instructions
RoCon+
RoCon+
RoCon+
These instructions
RoCon+
of more than
RoCon+
5.2.2
Start-up
INFORMATION
If the storage tank temperature falls below specific min-
imum values, the safety settings of the indoor unit prevent
the heat pump from being operated at low outside temper-
atures
- Outside temperature < -2 °C, minimum storage tank tem-
perature = 30 °C
- Outside temperature < 12 °C, minimum storage tank tem-
perature = 23 °C
Without backup heater:
The storage tank water must be heated to the required
minimum storage tank temperature with an external heater
booster.
With backup heater (EKBUxx):
At an outside temperature of < 12 °C and a storage tank
temperature of < 35 °C, the backup heater (EKBUxx) is
automatically switched on to heat the storage tank water to
at least 35 °C.
▪ To accelerate the heating process with backup heater,
temporarily set the [Config. of external heat source]
parameter = "1" and the [Ext. hot water power] para-
meter to the maximum value of the backup heater
[→ Main menu → Settings → Ext. source].
▪ In the [User] menu, select and switch on the [1x Hot Wa-
ter] parameter. After heating, switch the parameter off
again [→ Main menu → User → 1x load].
1
Check the cold water connection and, where necessary, fill the
potable water heat exchanger.
2
Switch on the power supply to the indoor unit.
Heat pump (indoor unit) with integrated heat accumulator
Chapter
Chap. 4.7
4.5.1
5.2
4.5.7
Chap. 5.1.3
Chap. 5.1.4
4.1
4.5.7
Daikin Altherma EHS(X/H)(B)-D
008.1444099_01 – 11/2018 – EN

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents