Install termination — concentric pipes
1. Assemble the vent termination as described for concentric
terminations, on page 40.
If necessary, you can shorten the lengths of the inner and
outer pipes for a shorter finished assembly. But you must
ensure the pipes butt correctly at both ends. Failure to
properly assemble the concentric termination can result
in flue gas recirculation, causing possible severe personal
injury or death.
2. Wall penetration:
a. Preferably, use a thimble with a 4½-inch hole. If not using a
thimble, carefully use a hole saw to cut a hole not larger than
4¾ inches in diameter through the wall. The finished hole
must provide a solid stop for the rain cap ribs, as shown in the
inset to Figure 31.
Ensure that the wall material is strong enough to prevent
the rain cap from being pushed inward if struck or
pushed from the outside.
3. Secure the termination in place so the rain cap will butt against the
outside wall or outer thimble plate as shown in Figure 31.
4. Before beginning vent and air piping from the boiler to the
concentric termination, mount and secure the concentric
termination as shown in Figure 31.
The vent and air piping must be securely supported, and
must not rest its weight on the boiler fittings. Failure to
properly support the vent and air piping could result in
vent piping damage, resulting in possible severe personal
injury, death or substantial property damage.
The supports/bracing used must support the termination
assembly to prevent slippage or movement. See
instructions provided with concentric kit for details.
The clamps used on the outside of the termination pipe
must not cut into the pipe or contain sharp edges that
could cause a crack to form.
When inserting the partially-assembled termination
kit through the wall penetration, wrap plastic or other
protection over the end of the exposed assembly to
prevent debris from entering the pipes. If the air passages
become blocked, the boiler will not operate. Once the
rain cap has been cemented to the assembly, there is no
way to correct the problem. The assembly would have
to be replaced if it were cut to be removed and cleaned.
Altering the assembly in any way could result in severe
personal injury or death due to toxic flue product
emissions.
If using AL29-4C stainless vent pipe, use the vent pipe
manufacturer's PVC adapter if connecting to a PVC
concentric vent attachment.
5. After the assembly has been positioned in the opening and all
supports have been attached, install a bird screen (purchased
separately if not included with the kit) and rain cap as follows:
a. Place the bird screen on the end of the inner pipe as in
Figure 44, page 40, or per concentric kit instructions for
polypropylene kits.
b. Cement the rain cap in place as shown.
Part number 550-142-190/1218
2
-
G
AS
FIRED WATER BOILER
Sidewall concentric
See notices on previous page.
— Boiler Manual
(continued)
Figure 30
Termination location — concentric
termination — multiple boilers —
clearance from vent of one to air intake of
the next
Figure 31
Installing and supporting the concentric
sidewall vent assembly
LEGEND
1
Vent pipe
2
Air pipe
3
Wall
4
Outer thimble plate
5
Supports every 5 feet
or per vent pipe mfg's
instructions
6
Wall brace, by installer,
(or see vent pipe mfg's
instructions)
7
Thimble, by installer
8
Rain cap
9
Rain cap ribs must butt
against outer thimble
plate or wall opening
31