Step 2 - Plan For Sequence Of Unit Installation; Step 3 - Inspect Unit; Step 4 - Provide Unit Support - Carrier WeatherMaster 50HC14 Installation Instructions Manual

Single package rooftop cooling only unit with puron (r-410a) refrigerant
Table of Contents

Advertisement

Step 2 — Plan for Sequence of Unit Installation
The support method used for this unit will dictate different
sequences for the steps of unit installation. For example, on
curb-mounted units, some accessories must be installed on
the unit before the unit is placed on the curb. Review the fol-
lowing for recommended sequences for installation steps.
CURB-MOUNTED INSTALLATION
1.
Install curb.
2.
Install field-fabricated ductwork inside curb.
3.
Install accessory thru-base service connection package
(affects curb and unit) (refer to accessory installation
instructions for details).
4.
Prepare bottom condensate drain connection to suit
planned condensate line routing (refer to Step 9 for
details).
5.
Rig and place unit.
6.
Install outdoor air hood.
7.
Install condensate line trap and piping.
8.
Make electrical connections.
9.
Install other accessories.
PAD-MOUNTED INSTALLATION
1.
Prepare pad and unit supports.
2.
Check and tighten the bottom condensate drain connec-
tion plug.
3.
Rig and place unit.
4.
Convert unit to side duct connection arrangement.
5.
Install field-fabricated ductwork at unit duct openings.
6.
Install outdoor air hood.
7.
Install condensate line trap and piping.
8.
Make electrical connections.
9.
Install other accessories.
FRAME-MOUNTED INSTALLATION
Frame-mounted applications generally follow the se-
quence for a curb installation. Adapt as required to suit spe-
cific installation plan.
Step 3 — Inspect Unit
Inspect unit for transportation damage. File any claim with
transportation agency.
Confirm before installation of unit that voltage, amperage
and circuit protection requirements listed on unit data plate
agree with power supply provided.
On units with hinged panel option, check to be sure all
latches are snug and in closed position.
Locate the carton containing the outside air hood parts; see
Fig. 13 and 14. Do not remove carton until unit has been
rigged and located in final position.
Step 4 — Provide Unit Support
ROOF CURB MOUNT
Accessory roof curb details and dimensions are shown in
Fig. 4. Assemble and install accessory roof curb in accor-
dance with instructions shipped with the curb.
NOTE: The gasketing of the unit to the roof curb is critical for a
watertight seal. Install gasket supplied with the roof curb as
shown in Fig. 4. Improperly applied gasket can also result in air
leaks and poor unit performance.
Curb should be level. This is necessary for unit drain to
function properly. Unit leveling tolerances are show in Fig. 5.
Refer to Accessory Roof Curb Installation Instructions for
additional information as required.
7

Advertisement

Table of Contents
loading

Table of Contents