Foreword Foreword This service manual describes the composition of the Model GS-600EX-1 truck crane, its adjustment methods and hydraulic and electric circuit diagrams. This service manual applies to the cranes with the specification numbers given below. Check the specification number on the nameplate of your crane. Read the separate operation and maintenance manual and the parts catalog for repair and maintenance of the crane in conjunction with this manual.
Page 3
Foreword 2. Outline of specifications Spec. No. Item GS-600E-1-90101 2M2D No. of boom sections No. of jib stages Single top Fitted Main winch Fitted Auxiliary winch Fitted Winch Winch brake Automatic brake (Neutral brake) Drum rotation indicator Visual- type (Option) Counterweight Integral with slewing frame Automatic Moment Limiter (AML)
Page 4
3. Group index Data, Adjustment and Checks System Diagrams WA04-4540E...
Page 5
Foreword 4. Contents Spec. No. Chapter Section GS-600E-1-90101 2M2D Data, Adjustment and Checks Service Data Adjusting Pressure (Hydraulic Pressure) Air Bleeding Procedure Adjustment Procedure (Electric) Operation Check (Crane Operation) Adjustment and Checks Inspection and Maintenance Boom Connecting Pin and Thread Size Table System Diagrams Hydraulic Circuit Electric Circuit (Upper)
Data, Adjustment and Checks Contents Y-1 Service Data ........1 Y-3 Air Bleeding Procedure ....14 Amounts of oil ..........1 Starting pump .......... 14 Before starting the engine......14 Operating speed ........1 Shakedown of the pump ......14 Hydraulic device ........1 Accelerator circuit ........
Y- 1 Service Data Service Data [NOTICE] Standard values are values at time of vehicle shipment from TADANO. Limit values are the limits at which adjustment or part replacement is necessary. 1. Amounts of oil (1L = 2.64172 × 10 gal)
Service Data 3.2 Hydraulic cylinder (1 m = 3.28084 ft) (1 mm = 3.93701 × 10 Remarks Standard Item value Condition and method Safety and notice Inspection conditions 1. Boom angle: 60°±2° (Lowering operation) 2. Boom full retraction 3. Engine stop 1°...
Y- 1 Y- 1 Service Data 4. Slewing section (1 mm = 3.93701 × 10 Item Standard value Remarks Horizontal play 4 mm or less Amount of slewing play Vertical play 2 mm or less Lateral rocking count 12 times or less 5.
Y- 1 Y- 1 Service Data 5.2 Boom bending and deformation (1 mm = 3.93701 × 10 Item Standard value (mm) Remarks Overall boom bending No significant vertical or horizontal Set the machine (at full extension, maximum elevation angle, with bends shall be found along the entire level.
Y- 1 Y- 1 Service Data 5.3 Jib bending and deformation (1 mm = 3.93701 × 10 △ 322-201-42000 Item Standard value (mm) Remarks Check for bending of the whole jib. a ≤ 9.9 a ≤ 1.5 + L /1000 No significant bending in vertical and L=8377 horizontal direction shall be found.
Y- 1 Y- 1 Service Data 5.5 Sheave (1 mm = 3.93701 × 10 Limit of minor Standard of minor Item diameter (mm) Remarks diameter (mm) (*1) Determination of limit minor ・Boom top diameter ・Single top (When rope of nominal diameter φ396 φ390.3 Only sheaves of the...
Y- 1 . Y-1. Service Data 6. Mass table The dry weights of the major components are shown in the table below. Check the weights, and select appropriate hoisting devices when removing and installing the component. Unit: kg (lb) Assembly name Mass Slewing frame assembly 5200 (11500)
1. Winch [NOTICE] Oil temperature: 50 ± 5°C (113 - 131°F) (Hydraulic oil: TADANO Hydraulic Oil LL) Confirm set pressure on the crane information screen in the maintenance mode of AML. Shift the control lever or switch while the engine is idling, then increase engine speed.
2. Telescoping and elevating [NOTICE] Oil temperature: 50 ± 5°C (113 - 131°F) (Hydraulic oil: TADANO Hydraulic Oil LL) Confirm set pressure on the crane information screen in the maintenance mode of AML. Shift the control lever or switch while the engine is idling, then increase engine speed.
3. Slewing [NOTICE] Oil temperature: 50 ± 5 °C (113 - 131°F) (Hydraulic oil: TADANO Hydraulic Oil LL) Confirm set pressure on the crane information screen in the maintenance mode of AML. Shift the control lever or switch while the engine is idling, then increase engine speed.
Adjusting Pressure (Hydraulic Pressure) 4. Outrigger [NOTICE] Oil temperature: 50 ± 5 °C (113 - 131°F) (Hydraulic oil: TADANO Hydraulic Oil LL) Shift the control lever or switch while the engine is idling, then increase engine speed. Engine Set pressure...
Adjusting Pressure (Hydraulic Pressure) 5. Remote control pilot pressure [NOTICE] Oil temperature: 50 ± 5 °C (113 - 131°F) (Hydraulic oil: TADANO Hydraulic Oil LL) Shift the control lever or switch while the engine is idling, then increase engine speed. Engine...
Y- 3 Y- 3 Air Bleeding Procedure Air Bleeding Procedure 3. Start the engine, warm up the engine, and then turn ON the PTO switch with the engine running at 1. Starting pump idling speed (600 min ) to shakedown the pump for approx.
Y- 3 Y- 3 Air Bleeding Procedure 2. Accelerator circuit Operation ass y , accelerator [NOTICE] When bleeding, make sure that the machine is set up horizontally. 1. Bleed the accelerator circuit by depressing the accelerator pedal in the crane operator’s cab repeatedly with the carrier engine stopped.
Y- 3 Y- 3 Air Bleeding Procedure 4. Winch circuit (main and aux.) 3.2 Slewing hydraulic pilot control valve Set the PTO switch and the slewing brake switch to [NOTICE] ON, and set the engine speed to the maximum (1250 Bleed the main and auxiliary winch circuits by following the procedures below.
Y- 3 Y- 3 Air Bleeding Procedure 5. Jib lock pin and jib mounting/stowing (offset) cylinder [NOTICE] Bleed the jib lock pin, jib offset cylinder as follows. (1) Start the engine, turn the PTO switch on, and raise the engine speed to approx. 1250 ± 15 min (2) Attach a hose to the air-bleed plug (A) and loosen the air-bleed plug.
Y- 3 . Y-3. Air Bleeding Procedure 6. Hydraulic pilot circuit 6.3 Telescoping AML vent solenoid valve (CN100) Pull out the connector (CN100) of the AML vent (Left rear of slewing table) solenoid. Set the hydraulic oil temperature to 50°C (122°F) or higher, set the PTO switch to ON, let the engine idle, and move the boom telescoping control lever fully to the retraction side.
Y- 4 Y- 4 Adjustment Procedure (Electric) Adjustment Procedure 1.2 2nd boom full retraction detection switch (CN553) (Electric) △ 323-503-42000 1. Detection switch adjustment Adjust the switch position so that its contact is shifted procedure (opened/closed) when the 2nd boom section is extended/retracted.
Y- 4 Y- 4 Adjustment Procedure (Electric) 1.3 Jib stowed detection switch (CN572) 1.4 Jib lock pin retraction detection switch (CN573) △ 323-503-42000 △ 323-503-42000 Adjust the switch position so that the dimension A Adjust the switch position so that the dimension A becomes 4 mm (0.16 in) with the jib stowed.
Y- 4 Y- 4 Adjustment Procedure (Electric) 1.5 Winch drum rotation detection switch 1.6 Over-left side detection switch (CN520) (main CN591, aux. CN592) △ 333-718-20000 △ 344-938-80000 △ 344-938-90000 Slewing the boom to the right side so that the Adjust the switch position so that the dimension A detecting surface of the proximity switch is above the becomes 2.5 ±...
Y- 4 Y- 4 Adjustment Procedure (Electric) 1.7 Control lever stand position detection switch 1.8 Over-unwinding detection switch (left) (CN529) (main) (CN595) and (aux.) (CN596) △ △ 344-912-83000 343-232-51000 △ 344-963-10000 Set the clearance B to minimum, and adjust switch Adjust the roller assy position by the bolt so that the position so that the dimension A becomes 2.5 dimension A becomes 6 mm (0.24 in), and lock the...
Y- 4 . Y-4. Adjustment Procedure (Electric) 1.9 Front outrigger swing out detection switch [Procedure] (left) (CN425), (right) (CN426) 1. Apply a thread locking agent (ThreeBond 1401 or △ 329-502-81000 the equivalent) to the threads of the proximity switch. [Condition] 2.
Y- 5 . Y-5. Operation Check (Crane Operation) 4. Outrigger emergency setting 1. Turn ON the emergency outrigger state register switch of the upper right panel in the cab. 2. Icon flashes on the AML display. 3. Check that the extension width smaller than the detected value can be registered on AML manually.
Y- 6 Y- 6 Adjustment and Checks Adjustment and Checks 1. Engine speed adjustment procedure 1.1 Speed control Potentiometer Output voltage ratio 50% position 1. Apply grease to the rotating part and the sliding area. Plate 2. Check the PTO is disconnected, and then start the engine.
Page 34
Y- 6 Y- 6 Adjustment and Checks 4. Adjust the cylinder rod length with nut D so that the gap C of the cylinder rod and the pin may have the play of 2 to 3 mm (0.08 to 0.12 in) at all retracting the cylinder rod manually.
Y- 6 Y- 6 Adjustment and Checks 1.2 Accelerator pedal 1. Remove the spring. 9. Depress the pedal unit the maximum engine speed (with no-load) can be secured, apply the 2. Adjust height H of the pedal to 175-185 mm bolt C to the pedal, screw in the bolt one turn from (6.9-7.3 in) with the end D and cylinder rod.
Y- 6 Y- 6 Adjustment and Checks 2. Adjusting boom telescoping wire ropes 1. With the boom fully retracted, tighten the nut-A until a tension is placed on the top boom section retraction wire rope (to keep the boom fully retracted). [NOTICE] Loosen the sway stopper bolt on the bottom of each boom...
Page 37
Y- 6 Y- 6 Adjustment and Checks 4. Tighten the nut-A until the top and 4th boom sections are fully retracted. 5. Extend the boom by 200 to 300 mm (8 to 12 in) by operating the boom telescoping control lever and then retract it fully.
Page 38
Y- 6 Y- 6 Adjustment and Checks 8. When the 4th boom section extension wire rope is tense: 8.1 Tighten nut-A by approx. a third turn. 8.2 Extend the boom by 200 to 300 mm (8 to 12 in) by operating the boom telescoping control lever and then retract it fully.
Y- 6 Y- 6 Adjustment and Checks 3. Install anti-buckling bolts for 10. Adjust the sway stopper bolt for the each boom section. telescoping cylinder 1. Connect the boom and telescoping cylinder using the pins A and B. 2. Adjust the bolt C locked with nuts D and E so that After retracting each boom section fully, lock the it can be turned by hand and the clearance (S) is bolt with a nut while it is lightly pressed against the...
Y- 6 Y- 6 Adjustment and Checks 4. Bubble level adjustment The upper bubble level in the cab and the lower bubble level on the outrigger control panel must be adjusted so that they are parallel to the slewing table plane (*1). The following shows the general adjustment procedure for bubble levels of large cranes (AC, RC and TC cranes).
Page 41
Y- 6 Y- 6 Adjustment and Checks ○Method B (Case where the machining surface on the slewing bearing cannot be used) 1. If the machining surface on the slewing bearing is not exposed, place bubble levels on the base plate on the slewing table with the boom directed to over-front.
Y- 6 . Y-6. Adjustment and Checks 4.2 Upper and lower bubble level adjustment After leveling the slewing table plane, adjust so that the bubble in each upper and lower bubble level is center-aligned to the mark using the adjuster screw of each bubble level with the boom directed to over-front and boom angle of 50°.
Y- 7 . Y-7. Inspection and Maintenance Inspection and Maintenance 1. Refer to “Inspection and Maintenance” in “Operation Manual” of its applicable crane. 2. Maintenance of Line Filter Maintenance table Inspection and Parts maintenance interval Parts name (used) Type of work Points/Quantity 600h 2400h...
Y- 8 . Y-8. Boom Connecting Pin and Thread Side Table Boom Connecting Pin and Thread Size Table (Unit: mm) (1 mm = 0.039 inch) Part Name Diameter Thread size Remarks Rod end pin Ø120 M33×3.5 Elevating cylinder Base pin Ø110 M30×3.5 M18×2.5...
Page 45
System Diagrams Contents Z-1 Hydraulic Circuit ......1 Z-3 Electric Circuit (Lower)....16 Comparison table of hydraulic parts (Part Composition of the electric circuit No., Part name and Location) ..1 diagram ........16 Hydraulic circuit diagram ......2 Comparison table (Connector No., Usage, Coordinate and Paragraph No.)...
Hydraulic Circuit Z - 1 Z - 1 “Location” shows each applicable paragraph No. of this manual’s contents. Refer to the contents. Hydraulic Circuit 1. Comparison table of hydraulic parts (Part No., Part name and Location) Parts Name Location Parts Name Location Parts Name Location...
Electric Circuit (Upper) Z - 2 Electric Circuit (Upper) 1. Composition of the electric circuit diagram The electric circuit diagram of this machine is made by the composition shown by following block diagram. In contents, it is divided into two paragraphs such as; Z-2 (Upper) and Z-3 (Lower). The electric circuit in the part of the block diagram drawn by a bold line is edited on the next page.
Electric Circuit (Upper) Z - 2 5) Shield line(GND) 2. Reading method of electric circuit diagram Wire to establish GND by diverging another wire to the 2.1 Notational convention shield line S ○○ – AA ■Conditions Signal distinction Wire number 1.
Page 55
Applicable serial No. : 291124-- : 291124-- Electric Circuit (Upper) : 291124-- : 291124-- 4. Electric circuit : 291124-- : 291124-- 4.1 Electric circuit (crane, main) [NOTICE] 1. If not specified, wire type is CAVS and wire size is 0.5mm 2.
Electric Circuit (Upper) Z - 2 Z - 2 [NOTICE] 1. If not specified, wire type is CAVS and wire size is 0.5mm 4.2 Electric circuit (ICF, SCT, GSMT) 2. This electric circuit is applicable if the ICF, SCT or GSMT is equipped. 3.
Electric Circuit (Upper) Z - 2 Z - 2 4.3 Electric circuit (center joint) [NOTICE] 1. If not specified, wire type is CAVS and wire size is 0.5mm △ 324-105-51500 WZ03-6151E...
Electric Circuit (Upper) Z - 2 Z - 2 △ Applicable serial No. :291124 -- 4.4 Electric circuit (slewing table, right) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.5mm △ 324-105-52000 WZ03-6151E...
Electric Circuit (Upper) Z - 2 Z - 2 △ Applicable serial No. :291124 -- 4.5 Electric circuit (slewing table, left) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.5mm △ 324-105-53000 WZ03-6151E...
Electric Circuit (Upper) Z - 2 Z - 2 4.6 Electric circuit (boom, bottom) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.5mm △ 324-105-54000 WZ03-6151E...
Page 61
Electric Circuit (Upper) Z - 2 Z - 2 4.7 Electric circuit (boom, top) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.5mm △ 324-105-55000 WZ03-6151E...
Page 62
Z - 2 . Electric Circuit (Upper) Z-2. Z-2. 4.8 Electric circuit (AML) [NOTICE] 1. If not specified, wire type is CAVS and wire size is 0.5mm △ 344-124-46000 WZ03-6151E...
Electric Circuit (Lower) Z - 3 Electric Circuit (Lower) 1. Composition of the electric circuit diagram The electric circuit diagram of this machine is made by the composition shown by following block diagram. In contents, it is divided into two paragraphs such as; Z-2 (Upper) and Z-3 (Lower). The electric circuit in the part of the block diagram drawn by a bold line is edited on the next page.
Page 65
Electric Circuit (Lower) Z - 3 Z - 3 Circuit Circuit Location Harness CN No. Usage coordinate page page page RA100 PTO signal relay RA101 Rotation signal relay Z-3 3.2 Z-11 2. RA102 N signal relay RA103 Transmitter power supply relay Left operation box power supply Right operation box power supply RB30...
Page 66
Electric Circuit (Lower) 3. Electric circuit 3.1 Electric circuit (carrier, main) ・SCANIA To electric circuit (junction to center joint) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.85mm 2.If the ICF, SCT or GSMT is equipped, refer to “3.2 Electric circuit (ICF, SCT, GSMT)”. YAZAKI 58X CN403 (05)8W...
Electric Circuit (Lower) Z - 3 Z - 3 [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.85mm 3.2 Electric circuit (ICF, SCT, GSMT) 2. This electric circuit is applicable if the ICF, SCT or GSMT is equipped. 3.
Z - 3 . Electric Circuit (Lower) Z-3. 3.3 Electric circuit (junction to center joint) [NOTICE] 1. If not specified, wire type is AVS and wire size is 0.85mm △ 326-525-93000 WZ03-7410E...
Z - 6 . Electric Parts Location Diagram (Upper) Z-6. Z-6. 6. Pressure switch installation diagram △ 323-603-33000 WZ02-6440E...
Page 93
Electric Parts Location Diagram (AML, Two-blocking) Z - 7 Z - 7 △ Applicable serial No. :291124 -- Electric Parts Location Diagram (AML, Two-blocking) 1. AML parts assy △ 323-503-42000 △ 323-603-31000 WZ02-5511E...
Page 94
Electric Parts Location Diagram (AML, Two-blocking) Z - 7 Z - 7 2. Two-blocking indicator assy (boom) △ 323-704-00000 WZ02-5511E...
Page 95
Electric Parts Location Diagram (AML, Two-blocking) Z - 7 Z - 7 3. Two-blocking indicator assy (single top and jib) △ 333-718-41000 △ 325-000-52000 WZ02-5511E...
Z - 1 1 . Harness (Lower) Z-11. Z-11. 6. Harness A (inside signal transmitter box) △ 326-525-02700 WZ04-4591E...
Page 124
Head Office Ko-34, Shinden-cho, Takamatsu, Kagawa, 761-0185, Japan International Service Group Tadano Ryogoku Bldg. 4-12, Kamezawa 2-chome, Sumida-ku, Tokyo, 130-0014, Japan TEL: +81-3-3621-7765 FAX: +81-3-3621-7785 Revision history Date Chapter (Page) Fed. 2018 Z (8)