7.3 Wiring Tab (Point to Point)
A point to point wiring tab drawing is provided to assist in troubleshooting the T-1000. The drawing
provides locations or all connection points and routings of wiring. See Dwg TC-T1000-S14.
7.4
110V Circuit
Circuit drawings are provided to assist in troubleshooting the functionality of the T-1000 and also the
interface signaling with auxiliary infeed equipment.
A circuit diagram of the 110V circuit is comprised of main power to the T-1000, through the fuse, Corcom
filter, motor controller, solid state relay, heater element, line out, and into the power supply printed circuit
board. See Dwg T1kSTNB-E1.
7.5 Analog Card, Temperature Controller, Heater Circuit
A circuit diagram of the Analog controller FPO-A21 with correct Dip switch settings is provided. See
Dwg T1kSTNB-E3. With a Thermocouple input (TC), the analog card has built in PID and auto tuning
functions with 16 bit resolution for very accurate temperature controls. See Dwg T1kSTNB-E3.
7.6 Stepper Motor Circuit
A circuit diagram of the stepper motor controller is provided with correct Dip switch and Pot settings. See
Dwg T1kST-E4.
7.7 Perforation Sensor PCB
APPI manufactures the printed circuit board for accurate and consistent perforation detection, for accurate
bag positioning and registration. A circuit diagram is provided for this PCB. See Dwg T1kSTNB-E5.
7.8 Aux Interface
APPI provides for a closed loop signal with auxiliary infeed equipment. The circuit diagram references the
pinouts on Aux 2 connector, located on the T-1000 rear electrical panel (military connector). See Dwg
T1kST-E7.
7.9 Solenoid Valve Circuit Diagram
The T-1000 is equipped with an expandable Valve manifold, pre wired for up to 7 options solenoid valves.
Valve stations 1 through 4 are standard, and valve station 5-11 are options. PLC output information,
DB25 pin outs, voltages and valve descriptions are provided on this circuit diagram. See Dwg T1kST-E8.
7.10 Pneumatic Piping Diagram
APPI offers a piping diagram to assist in troubleshooting the T-1000 bagger. Piping from Solenoid Valve
Stations 5 through 11 will change based on the configuration of the T-1000 and the options ordered by the
customer. See Dwg PL-S14.
139