SUN2000 (8KTL-28KTL)
User Manual
Context
Good grounding for the SUN2000 helps resist the impact of surge voltage and improve EMI
performance. Connect the PGND cable before connecting the AC power cables, DC power
cables, and communications cables.
It is recommended that the ground cable be connected to a nearby ground position. For a
system with multiple inverters connected in parallel, connect the ground points of all inverters
to ensure equipotential connections.
A ground terminal has five parts, as shown in
Figure 5-1 Ground terminal composition
(1) M6 welded stud
Procedure
Step 1 Remove an appropriate length of the insulation layer from the PGND cable using a wire
stripper, as shown in
Figure 5-2 Stripped length
Note: L2 is 2 mm to 3 mm longer than L1.
Step 2 Insert the exposed core wires into the conductor crimp area of the OT terminal and crimp
them using a crimping tool, as shown in
Recommended OT terminal: OT-6 mm
Issue 10 (2017-07-30)
If the installation location is near the ground, connect the PGND cable to the ground before installing the
SUN2000.
(2) OT terminal
Figure
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
Figure
(3) Flat washer
5-2.
Figure
5-3.
2
or 10 AWG-M6.
5 Electrical Connections
5-1.
(4) Spring washer
(5) Nut