4.2 Commissioning and startup wizard

4.2.1 Commissioning steps:

1. Read safety instructions on page 1
2. Secure the grounding and check that cables
comply with requirements
3. Check quality and quantity of cooling air
4. Check that all start / stop switches are in
STOP position
5. Connect the drive to mains
6. Run the Startup wizard and set all necessary
parameters
Table 4.1: Commissioning steps

4.2.2 Startup wizard

Vacon 10 runs the startup wizard in first power-up. The wizard can be run by setting
SYS Par.4.2 =1. The following figures show the procedure.
NOTE! Running the startup wizard will always return all parameter
Figure 4.2: Vacon 10 startup wizard (standard application)
4
settings to their factory defaults!
RUN
READY
STO P
ALARM
REF
MON
PAR
SYS
FWD
REV
I/O KEY PAD
1
Enter Par. menu, select
P1.3 motor nominal speed
READY
RUN
S TO P
ALARM
REF
MON
PAR
rpm
SYS
FWD
REV
I/O KEY PAD
OK
P1.3
3
Change
value
with Up/Down button
and press OK to
comfirm
navigation & startup
7. Perform test run without motor, see the
User Manual at www.vacon.com
8. Run no-load tests without motor being con-
nected to the process
9. Perform an identification run (Par. ID631)
10. Connect the motor to the process and per-
form test run once again
11. Vacon 10 is now ready for use
FAU LT
READY
RUN
REF
MON
PAR
SYS
BUS
FWD
REV
2
Press OK enter
edit mode
FAU LT
READY
RUN
REF
MON
PAR
SYS
BUS
FWD
REV
4
Perform the same
procedure for P1.4,
motor nominal current
Tel. +358 (0)201 2121 • Fax +358 (0)201 212205
STO P
ALARM
FAU LT
I/O KEY PAD
BUS
OK
S TO P
ALARM
FAU LT
I/O KEY PAD
BUS

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the 10 and is the answer not in the manual?

Table of Contents