Inspection Prior To Putting Into Service For The First Time; Inspections When First Putting Into Service, Handing Over - DEMAG DC-Com 1 Operating Instructions Manual

Chain hoist
Hide thumbs Also See for DC-Com 1:
Table of Contents

Advertisement

6.3

Inspection prior to putting into service for the first time

Before putting into service for the first time, the owner is obliged to carry out the following inspections:
Action
Check continuity of the PE conductor connection
Check emergency stop device
Check direction of movement
Check 7-segment display
Check chain lubrication (under arduous conditions, the chain must be lu‐
bricated more frequently)
Check function of operating limit switch for lifting
Check function of operating limit switch for lowering
Check swich-off buffer / switch-off spring / operating limit switch actuator
Check control cable and control pendant housing for damage
Check operation of the brake
Check hook and hook safety catch
Tab. 41
6.4

Inspections when first putting into service, handing over

WARNING
Impermissible operation
There is danger to life and limb when the machine is operated without previous inspection.
Machines may only be put into service, when they have been inspected according to the accident prevention
regulations.
By means of suitable measures carried out by the owner or on his behalf, the owner ensures that the load handling
attachments and machinery ready for operation function in complete safety before first being put into service. The
specified measures must allow for the static and dynamic features of the machinery.
The following checks must be carried out when first putting into service:
● The proper condition of the supporting structure and the load capacity of the chain hoist.
● Safety devices must be completely fitted and effective.
● Clearances and safety distances must be complied with.
● The emergency stop device must be checked by actuating the emergency stop.
When putting into service for the first time, all possibilities of intended use must be checked at the corresponding
maximum permissible load. The functioning of the safety devices must be checked (e.g. by lifting an overload). At
the same time the behaviour of the chain hoist in the case of misuse must be checked.
Before handing over, different inspections of the machine must be arranged for:
● Inspection for suitability for operation
● Acceptance test
As soon as the safe operating status of the chain hoist is ensured, the test and inspection records can be prepared.
When handing over the machine, the test and inspection records (test and inspection booklet; observe the relevant
country-specific regulations) are handed over.
After the machine has been handed over, it may be used as intended.
60
Section
-
-
⇒ "Line connection", Page 48
⇒ "7-segment display for operating status and error dis‐
play", Page 31,
⇒ "Software version, operating hours, number of cycles,
operating statuses", Page 31
⇒ "Available hoist chains", Page 83
⇒ "Checking the operating limit switches", Page 77
⇒ "Checking the operating limit switches", Page 77
⇒ "Checking the swich-off buffer / switch-off spring",
Page 91,
⇒ "Checking the operating limit switch actuator",
Page 78
-
-
⇒ "Checking the load hook", Page 88
Inspec‐
tion
X
X
X
X
X
X
X
X
X
X
X

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Dc-com 2Dc-com 10Dc-com 5

Table of Contents