Commissioning

888529803
Commissioning cannot take place without testing being conducted by a qualified per-
son!
• Before you place the system in which you use a samosPRO safety control in operation for
the first time, it must be tested and documented for release by a qualified person.
ATTENTION
Monitor the hazardous area!
• Before commissioning, make sure that no one is inside the hazardous area.
• Check the hazardous area and secure it against access by unauthorized people (e.g. place
warning notices, set up blocks, etc.). Note the corresponding laws and local regulations.
ATTENTION
9.1

Total acceptance of the application

888531339
You may only place the system into operation if the total acceptance inspection was passed
successfully. The total acceptance inspection may only be done by appropriately trained per-
sonnel.
The total acceptance comprises the following test points:
Procedure
 Check whether all of the safety-related parts of the system (wiring, connected sensors and
command encoders, configuration) meet the respective standards (e.g. EN 62061 or EN
ISO 13 13849-1).
 Test the devices connected to the safety control in accordance with the test information in
the corresponding operating instructions.
 Mark all of the connections (connection lines and plug connectors) on the safety control
clearly and uniquely to prevent mixups. Because the samosPRO system has multiple
connections with the same shape, make sure that connection lines or connectors that are
disconnected are not unintentionally connected back to the wrong connection.
 Check the signal paths and the correct integration into higher-level controls.
 Check the correct data transmission from and to the samosPRO safety control.
 Check the logic program of the safety control.
 Carry out a complete validation of the safety functions of the system in each operating
mode and an error simulation. Note in particular the response times of the individual appli-
cations.
 Fully document the configuration of the system, the individual devices, and the results of
the safety check.
 To prevent unintentional overwriting of the configuration, activate the write protection of
the configuration parameters in the samosPRO system. Changes are only possible if the
write protection has been canceled.
9.2

Tests before initial commissioning

888532875
The tests before initial commissioning are used to confirm the safety requirements required in
the national/international guidelines, particularly the Machinery or Work Equipment Directive
(EC conformity).
Procedure
 Test the effectiveness of the safety equipment on the machine in all operating modes and
functions that can be set on the machine.
 Make sure that operating personnel who will be working with the machine protected by
the safety control are trained by qualified people from the machine operator before starting
work. The machine operator is responsible for the training.