Installing The S8 Chassis; Order Of Installation - Enterasys S8-Chassis-POE4 Hardware Installation Manual

S-series
Table of Contents

Advertisement

Installing
the S8 Chassis
 
The following sections describe the procedures that you must follow to complete the installation 
of the S8 chassis.

Order of Installation

Once you have chosen a suitable site, you can install the S8 chassis as a freestanding or rack‐
mounted unit. If you are installing an S8 chassis with a PoE subsystem, ensure that you have read 
the precautions in "Precautions" on page 2‐2.
1.
For a freestanding installation, install the rubber feet (Installing Rubber Feet). 
If you are rack mounting the S8 chassis, start at step
2.
(Optional) Install the mid‐mount brackets (Installing the Mid‐mount Brackets).
3.
Mount the chassis in a 48.26‐centimeter (19‐inch) rack or other secure location (Rack Mounting 
the S8 Chassis).
4.
(Optional) Install the cable management clips (Installing the Cable Management Clips).
5.
Attach the Electrostatic Discharge wrist strap (Attaching the Electrostatic Discharge Wrist 
Strap).
6.
Install the AC power supplies (Installing the S‐AC‐PS Power Supplies).
7.
Power up the S8 chassis (Powering up the S8 Chassis).
8.
If you are using PoE, install the PoE power supplies (Installing the S‐POE‐PS Power Supplies 
in the PoE Subsystem).
9.
Power up the PoE power supplies (Connecting Power to the S‐POE‐PS Power Supplies).
Note: To reship the chassis, refer to the directions above and reverse each step.
2. 
Enterasys S-Series S8 Chassis Hardware Installation Guide 3-3

Installing the S8 Chassis