    Contents Overview Pre-testing Guidelines Daily Maintenance Weekly Maintenance Six Monthly Maintenance Annually Maintenance Four-Five Yearly Maintenance Battery Information Fire Control Panel / PSU Batteries Page 2 of 10...
  • Page 3: Overview

    Overview It is important that re alarm systems are regularly checked to ensure their continued correct operation. The maintenance of re alarm systems should be in accordance with applicable local installation codes. This maintenance guide has been written in conjunction with British Standard BS5839: Part 1.
  • Page 4: Pre-Testing Guidelines

    Pre-testing Guidelines It is important to ensure that operation during testing does not result in a false re alarm. If the re alarm system is connected to an automatic dialling unit, then transmission should be prevented (for instance by disconnection) before the routine test is carried out, since under normal conditions test calls are not permitted.
  • Page 5: Weekly Maintenance

    Weekly Maintenance These checks would normally be carried out by a responsible member of the building sta . They should also be carried out by the service engineer after all routine maintenance checks. WARN ALL PERSONNEL THAT THE SOUNDERS ARE ABOUT TO BE TESTED. TELEPHONE CENTRAL STATION AND INFORM THEM THAT A TEST IS ABOUT TO TAKE PLACE Note: When reference is made to the controller, the actions should be carried out / checked on all...
  • Page 6: Six Monthly Maintenance

    Test all call points and 50% of automatic devices and con rm correct operation as detailed in weekly tests point Check device signal strength readings against the recorded commissioning levels as per FireCell minimum requirements. Check all fault indicators by simulating a FAULT condition in each zone either: Removing a detector from its base.
  • Page 7: Annually Maintenance

    Yearly Maintenance Note: When reference is made to ancillary equipment, the actions should be carried out / checked on all Radio Cluster Communicator units tted on the system and also the Radio Hub were applicable. The following checks should be made:- a) Carry out all six monthly checks.
  • Page 8: Four-Five Yearly Maintenance

    Four-Five Yearly Maintenance The following checks should be made:- Carry out all annual checks. Inform the responsible person that “x” number of batteries require to be replaced. Replacement batteries are required in the following equipment; All Radio Type Device Variants Radio Cluster Communicators The Battery Information section refers to recommended replacement battery requirements.
  • Page 9: Battery Information

    Battery Information FireCell Equipment Type Typical Battery Life Batteries Required Part Number(s) FireCell Control Panel/PSU Up to 5 years* As per system design† Up to 5 years*‡ 1x 6V 4Ah FC-006-004 Callpoint Up to 5 years* 6 x AA Alkaline cells...
  • Page 10 The information contained within this literature is correct at time of publishing. The EMS Security Group Ltd reserves the right to change any information regarding products as part of its continual development enhancing new technology and reliability. The EMS Group advises that any product literature issue numbers are checked with its head o ce prior to any formal speci cation being written.