10 THINGS TO THINK ABOUT BEFORE INSTALLING
Have you completed a site survey to determine if any site
changes are required?
o On-line type UPS for Exciter, Audio Processors, Ethernet, STL,
Remote Control, etc
o AC mains service panel size and OSHA considerations.
o Remote control capacity and configuration
o Room lighting
o Work surface
o Telephone service with headset phone for accessing support.
o Size of building
o Storage of documents and spare parts
Do you have experience in installation of Transmitters and
Transmission line?
o Site grounding configuration
o Tools and craft skills to cut and assemble rigid line.
o Coordinate with electrician to connect AC service to transmitter.
o Any tower/antenna work considerations/tower crew contacted.
Have you considered the additional heat gain in your building
when adding the HD equipment?
o Temperature alarm connected to remote control
o Redundant cooling equipment
o drip pan with drain for split systems to protect equipment below
evaporator
o Reject loads (if used) location.
o Addition HVAC may be needed.
Do you own or have access to test equipment to measure and
monitor HD performance?
o High dynamic range digital spectrum analyzer with averaging and
narrow RBW.
o HD receiver with split mode
o Does the site have non-functioning test equipment that needs
removal?
WARNING: Disconnect primary power prior to servicing.
HD SYSTEMS
888-2587-001
4/18/11