Warnings And Precautions; Rack Precautions; General Server Precautions - Supero SC826BE1C-R920LPB User Manual

Sc826 series chassis
Table of Contents

Advertisement

SC826 Chassis Manual
5-3

Warnings and Precautions

Rack Precautions

Ensure that the leveling jacks on the bottom of the rack are fully extended to
the floor with the full weight of the rack resting on them.
In single rack installations, stabilizers should be attached to the rack.
In multiple rack installations, the racks should be coupled together.
Always make sure that the rack is stable before extending a component from
the rack.
Only one chassis should be extended from the rack at a time. Extending two or
more chassis simultaneously may cause the rack to become unstable.

General Server Precautions

Review the electrical and general safety precautions that came with the
components you are adding to your chassis.
Determine the placement of each component in the rack before you install the
rails.
Install the heaviest server components on the bottom of the rack first, and then
work upward.
Use a regulating uninterruptible power supply (UPS) to protect the server from
power surges, voltage spikes and to keep your system operating in case of a
power failure.
Allow the hot-swappable hard drives and power supply modules to cool before
touching them.
Always keep the rack's front door and all panels and components on the servers
closed when not servicing to maintain proper cooling.
5-2

Advertisement

Table of Contents
loading

Table of Contents