3 FILLING THE SYSTEM
T000181-B
T000182-A + LT.AL.W7H.000.224
T000185-A
LT.NL.W6H.000.114 + LT.AL.W7H.000.235
126582-160412
Add water to the installation if necessary. To do this, proceed as follows:
1. Open the valves on all radiators connected to the heating system
2. Set the room thermostat to as low a temperature as possible.
230 V
3. Switch off the boiler electrical power supply.
4. Wait until the temperature drops below 40°C and the radiators seem cold before
filling the heating system.
5. Open the filling loop valve.
6. Close the filling loop valve when the manometer indicates the design operating
pressure.
7. After filling the installation, switch the boiler on.
8. Set the room thermostat or the regulator.
9. Set the radiator valves.
3. Filling the system