z10 BC IMPP
Site Preparation Checklist
Task/Consideration
CHECKPOINT 5
Air conditioning installation is complete
capacity and controls provided for automatic temperature and humidity levels
filtration system is adequate and maintenance plan established
regular monitoring and testing
Training for computer room personnel
If you have elected to do your own I/O cabling, as cables begin to
arrive, start installing and labeling them. Label power receptacles
as they are installed
Complete the Systems Assurance Product Review with your IBM
marketing representative or Business Partner and the system installers
Carefully measure the delivery path from the shipper drop-off point
to the raised floor install location. Accurate measurements now may
prevent installation delays later
CHECKPOINT 6
Complete communication equipment installation,
cables, modems, switches, telephones, connection panels, etc
Complete the Remote Support Facility installation
LAN and communication cables, switches, patch panels, etc
Prepare IOCP input statements or HCD definitions
Use the CHPID Mapping Tool on Resource Link to help assign
PCHIDs to CHPIDs
If you have elected to do your own I/O cabling, complete the checkout
of system cables as much as possible. Verify that the cables are
properly routed, protective end caps are in place, that the processor
ends of the cables are safely out of the way for system installation,
and that cable safety procedures are followed
Complete the checkout of the power cables. Test for continuity and
polarity, proper grounding, correct phase wiring, and general power
safety considerations
Complete the required changes to the existing programs and data
processing units
Install communication facilities, such as telephone lines and modems
Level 03c, May 2011
Task Assigned
Target Date
Completed
( )