Commissioning
Menu 2 parameter
2.7A Demand /fault
0 = The blue light will only operate as a
flashing fault alert.
indicator
1 = The blue light will operate as a boiler
(blue light) activation
demand light and fault alert.
This is set to 1 by default.
Reset to factory settings
To reset any or all changes made in Menu 2 back to the factory default
setting:
Any changes made to Menu 1 are not reset by these
actions.
1. Press and hold the
ok
seconds. The screen will then display code BE and spanner symbol.
1
Fig. 58
reset
1. Press the
button and "reset" will be displayed with the tick
symbol for three seconds. After three seconds the display will revert
to the normal operation screen.
APPLIANCE MUST BE SET TO CO
Air settings are approximate, as flue length and nozzle
variations will affect them.
Nominal boiler rating at normal operating temperature using Kerosene (Class C2)
Oil pump pressure
Nozzle
bar
psi
Greenstar Heatslave II 12/18 model
0.35 x 80° SR
9.0
132
0.45 x 60° ES
7.5
110
0.55 x 80° ES
7.8
115
Greenstar Heatslave II 18/25 model
0.50 x 80° ES
8.5
125
0.60 x 60° ES
8.5
125
0.75 x 80° ES
7.5
110
Greenstar Heatslave II 25/32 model
0.75 x 80° ES
7.5
110
0.75 x 80° ES
10.0
147
0.85 x 80° EH
9.5
140
Table 8 Combustion settings
30
and
buttons for at least five
LEVELS.
2
Approximate
flue gas
Fuel flow rate
temperature
Kg/h
l/h
°C
1.04
1.32
72
1.28
1.63
77
1.54
1.96
80
1.58
1.96
76
1.84
2.33
81
2.15
2.72
87
2.15
2.72
79
2.46
3.12
81
2.78
3.52
86
2
Fig. 59
Finish pre-commissioning boiler checks
▶ Check the CO
levels, refer to table 8 and adjust the air shutter [L].
2
▶ Check the flue gas temperature is close to the values in table 8.
If the flue gas temperature is too high and the baffles are correctly fitted,
then reduce the oil pump pressure [B] 5-10 p.s.i. to compensate for
nozzle variations.
▶ Turn off the electrical supply.
▶ Isolate the oil supply to the burner.
▶ Remove the oil pressure gauge.
▶ Refit the blanking plug [A].
▶ Check and rectify any oil leaks.
3. Switch on the oil supply.
▶ Switch on the electrical supply.
▶ Restart the boiler and run for 5 minutes.
▶ Recheck the CO
levels and if required, adjust the air shutter
2
setting [D] to obtain the correct CO
▶ Refit the sample point cap (hand tighten only, do not over tighten)
and refit the burner cover.
▶ Complete the oil boiler commissioning checklist at the back of this
manual.
RIELLO
RDB OIL PUMP
C
B
A
A - B leed & pressure gauge port
B - Pressure adjustment
C - Vacuum gauge port
Fig. 60
Approximate
Input
air setting
(appliance)
%CO2
kW
11.0
3.0
12.4
11.5
5.0
15.4
12.0
5.0
18.5
11.5
3.0
18.5
12.0
3.5
22.1
12.0
4.5
25.7
11.5
3.5
25.7
12.0
4.5
29.4
12.5
5.0
33.0
Greenstar Heatslave II External
level.
2
3
D
6 720 805 209-46.1TL
Output
Air damper
(appliance)
disk setting
Burner head
kW
12.0
12/15
LD2X Short
15
12/15
LD2X Short
18.0
18
LD2X Short
18.0
18
LD2SX Short
21.5
21.5
LD2SX Short
25.0
25
LD2SX Short
25.0
N/A
T2 Short
28.5
N/A
T2 Short
32.0
N/A
T2 Short
ErP -
6 720 813 345 (2014/09)

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents