close the front door, re-position and fasten the front rack posts 6.5 inches (165 mm) back towards
the rear of the rack to leave space for the brackets.
2.
Determine the height at which you want to mount the chassis in the equipment rack.
3.
Install the rack bar on the front posts just below the desired height of the bottom of the chassis. The
rack bar requires 1 RU below the chassis.
Use the rack bar as a guide to mount the chassis. It is not required to support the weight of the
chassis; you can remove it when the chassis is securely mounted in the rack.
Hold the rack bar (item 1 in Figure 2) so that the smooth side faces outward and the arrows point
upward. Attach the bar to the front-rack posts using the mounting screws and washers provided with
the rack bar (items 2 and 3 in Figure 2).
NOTE: The installation procedure in this section describes how to install the C9010 in a 2-post
rack using the rack bar provided in the base configuration package. For information about how
to use Dell ReadyRails or a rack mount tray to install the C9010, follow the instructions in
Installing Dell ReadyRails
Figure 2. Installing a Rack Bar in a 2-Post Rack
Installing the Hardware
or
Installing a Rack Mount
Tray. Then continue with Step 4.