WARNING: ENSURE THAT THE FIBERGLASS
!
ROPE GASKET SUPPLIED WITH THE
FIREPLACE SEALS BETWEEN THE FIRST VENT
COMPONENT AND THE OUTER FIREPLACE WRAP.
If the installation is for a termination cap attached directly
to the fireplace, skip to the sections, Install Firestops and
Vent Termination.
2. Continue Adding Vent Components
WARNING: INSTALLATION OF THIS FIRE-
!
PLACE REQUIRES THE USE OF HEAT
SHIELD 570-290 ABOVE THE FIRST 90
THE VENTING SYSTEM.
To Install the Heat Shield:
1. Determine if the heat shield is required. Do so by mea-
suring the vertical distance between the top horizontal
surface of the elbow to any combustible surface above.
If the distance is more than 4 inches, the heat shield is
NOT required. If it is 4 inches or less, the heat shield IS
REQUIRED. Install per the following steps. See Figure 20.
HEAT
SHIELD
Figure 20
2. Fasten the shield in place using the four pilot holes pro-
vided in the part. The shield should be oriented such that
the 13 1/8 inch dimension (longest dimension) is run-
ning in the same direction the elbow is pointing. The
shield should be centered directly above the elbow, and
positioned so that it creates a 1/2 inch airspace between
the shield and the combustible surface. See Figure 21.
CORRECT
COMBUSTIBLE SURFACE
HEAT SHIELD
Figure 21
0
ELBOW IN
COMBUSTIBLE
SURFACE
3" MIN.
(76mm)
INCORRECT
DIRECTION
UP
0
90 ELBOW
• If the combustible materials are not in place at the time
of install the elbow heat shield may be screwed to the
exhaust pipe (see Figure 22). Cut the tabs as shown
and bend down. Using the screws found in the manual
bag secure the heat shield to the pipe maintaining 3" to
4" between the pipe and shield.
SCREW
3"
(76mm)
Figure 22
• Continue adding vent components, locking each succeed-
ing component into place.
• Ensure that each succeeding vent component is secure-
ly fitted and locked into the preceding component in the
vent system.
• 90° elbows may be installed and rotated to any point
around the preceding component's vertical axis. If an el-
bow does not end up in a locked position with the pre-
ceding component, attach with a minimum of two (2)
sheet metal screws.
Figure 23. Adding Venting Components
3. Install Support Brackets
For Horizontal Runs - The vent system must be supported
every five (5) feet of horizontal run by a horizontal pipe support.
To install support brackets for horizontal runs:
• Place the pipe supports around the vent pipe.
• Nail the pipe supports to the framing members.