5-4. Taping the Tubes

(1) At this time, the refrigerant tubes (and electrical wiring
if local codes permit) should be taped together with
armoring tape in 1 bundle. To prevent the
condensation from overfl owing the drain pan, keep the
drain hose separate from the refrigerant tubing.
(2) Wrap the armoring tape from the bottom of the
outdoor unit to the top of the tubing where it enters the
wall. As you wrap the tubing, overlap half of each
previous tape turn.
(3) Clamp the tubing bundle to the wall, using 1 clamp
approx. each ft. (Fig. 5-10)
NOTE
Do not wind the armoring tape too tightly since this will
decrease the heat insulation effect. Also ensure that the
condensation drain hose splits away from the bundle and
drips clear of the unit and the tubing.

5-5. Finishing the Installation

After fi nishing insulating and taping over the tubing, use
sealing putty to seal off the hole in the wall to prevent rain
and draft from entering. (Fig. 5-11)
VRF_Indoor_US.indb 74
VRF_Indoor_US.indb 74
Fig. 5-10
Apply putty here
Fig. 5-11
74
Clamp
Insulated tubes
Drain horse
Tubing
2011/09/30 12:23:13