4

Installing the boiler

4
Installing the boiler
This chapter describes how to install and place the boiler
in the boiler room.
Caution: Risk of system damage from freezing.
V Install the heating system in a frost-free
room.
4.1

Wall clearances

Position the boiler with the recommended wall clear-
ances. Reducing the minimum clearances makes the
boiler more difficult to access during installation, mainte-
nance and cleaning.
The boiler base or foundation must be perfectly flat and
level.
The burner door is factory-fitted with the hinges on the
right. The burner door can be converted to open to the left
(Chapter 4.2, page 15).
Dimen-
sion
A
Recommended
minimum
B
Recommended
minimum
C
Recommended
minimum
L
Chapter 2.7.1 "Logano G115 WS
K
dimensions", page 8
Tab. 10 Recommended and minimum wall clearances
(dimensions in inches).
The boilers are designed for a side clearance
of 6".
Where applicable, allow extra wall clearanc-
es for additional components such as DHW
tank, pipe connections, flue gas silencer or
other flue components, etc.
Caution: Risk of fire from flammable materi-
als or liquids.
V Clearances less than 6" must comply with
local and statutory codes.
V Make sure that there is a sufficient clear-
ance between combustible materials and
the chimney connection as specified by
NFPA 31 (distance of 18 ").
V The floor must comply with the require-
ments of NFPA 31.
14
Wall clearance
51-1/8"
39-3/8"
27-½"
15-¾"
15-¾"
3-7/8"
Logano G115 WS US/CA - Technical specifications are subject to change without prior notice.
Fig. 7
Boiler room clearances (boiler positioned on the
l.h. or r.h. side)
7 747 019 141-07.1RS

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Logano g115/3 wsLogano g115/4 wsLogano g115/5 ws

Table of Contents