4.2.4 Sequence Power-On/Off Time tab

Figure 29: Power Management – Sequence Power-On/Off Time tab
Power-On/Off Policy box
Enable Sequence Power-On/Off Time
Enables/disables time-delayed power-on/off for server blades.
I
If the system is populated with storage blades, they are excluded from the power-on/off
sequence.
Server Blade Power-On Delay After System Unit Power-On (0 - 60)
The time-delayed power-on/off of the participating server blades starts after the time (in minutes) has
been specified here.
Participating Server Bays
Here you can select the server blades which are to be powered-on/off with time delay.
Power-On Sequence box
Server Blade Power-On Sequence
Configure the sequence by switching the participating server blades to the right window and
rearrange them in the intended ascending order.
Delay Between Two Server Blades (0 - 10)
Specifies the time delay from the power-on of a server blade to the power-on of the next server blade.
Power-Off Sequence box
Server Blade Power-Off Sequence
Configure the sequence by switching the participating server blades to the right window and
rearrange them in the intended ascending order.