10.2 Insulating the connection and header pipes

B Cut enclosed insulation (710 mm long) into 88 mm
lengths and place around the corrugated pipe con-
nectors between the collectors.
Insulation of the manifolds in internal or external
installations
– For the insulation of external pipework, use only UV
and high temperature resistant insulating materials,
rated to 150 °C.
– For the insulation of internal pipework, use only high
temperature resistant insulating materials, rated
to 150 °C.
– Make the insulation bird-proof.