Maintenance
Machine ____________________________
Operator ___________________________
1. Inspect water inlet valve hose connections on the
back of the machine for leaks.
2. Inspect steam hose connections for leaks (where
applicable).
3. Verify that insulation is intact on all external
wires and that all connections are secure.
4. Inspect door lock and interlock before starting operation:
a. Attempt to start the machine with door open.
b. Close the door without locking it and attempt
to start the machine.
c. Close and lock the door, start a cycle, and
attempt to open the door while the cycle is
in progress.
1. Clean the air intake filters.
2. Clean the door gasket of all foreign matter.
3. Flush the supply tanks.
4. Clean the machine's top, front, and side panels.
5. Leave loading door open at the end of each day to
allow moisture to evaporate.
6.
7.
NOTE: Leave loading door open after each completed cycle to allow moisture to evaporate.
NOTE: Unload the machine promptly after each completed cycle to prevent moisture buildup.
3–6
Daily Preventive Maintenance Checklist
Checks
OBSERVE ALL SAFETY WARNINGS!
Beginning of Day
End of Day
Week of: ________________
Days
1
2
3
4
5
6
7
F232048

Advertisement

Table of Contents
loading

Related Products for Raytheon UY75

This manual is also suitable for:

Uy160Uy230

Table of Contents