Installation on an existing concrete floor may
be accomplished using either expansion bolts
or J-bolts. An elevated base frame may also be
used to raise the machine if desired. In each
case, the floor must be at least 4" (102 mm)
thick and of good quality. If the floor fails to
meet the above requirements, a concrete
foundation pad must be constructed.
Note: Improper installation may void the
warranty. Consult the manufacturer or the
distributor before deviating from the following
procedures.

Expansion Bolt Installation

Note: If the floor is not level and even, use
J-bolts and machinery grout to ensure a stable
installation.
Use the following instructions and Figures 2–5
through 2–10 as a guide to step-by-step
installation of the expansion bolts.
1. Verify that the floor is at least 4" (102 mm)
thick and of good quality. If the floor fails
to meet the above requirements, a concrete
foundation pad must be constructed.
2. Use the base of the machine as a template
by positioning the machine in the desired
location and marking the pre-drilled
mounting holes on the floor. See Figure 2–
5.
F232048
Figure 2–5.
3. Set the drill depth gauge to 2-9/16" (65
mm). See Figure 2–6.
Figure 2–6.
4. Drill the holes to the set depth. See Figure
2–7.
Figure 2–7.
Installation
2–13