COMMISSIONING

The whole of the gas installation, including the meter,
should be inspected, purged and tested for soundness in
accordance with the codes of the Country of destination .
1 . Ensure that all controls are in the " " position and turn
on the main gas supply .
2 . Remove the grease drawer & upper & lower fascia panels
and connect a U-gauge manometer to the pressure test
point on the main manifold . Operate the main burners in
accordance with the instructions given in the Operation
Instructions .
3 . Check that the supply pressure is correct . If necessary,
adjust the supply pressure to give the required setting .

Burner Adjustments

Fixing Screw
Required Length
of Opening
Page 10
Minimum Flame Setting
1 . Set gas tap to low " " position .
2 . Connect a U-gauage manometer to the pressure test
3 . With a screw driver, turn the adjuster on the tap body
When all the settings have been checked, remove the
U-gauge manometer, replace the pressure test point screw
and the front panels .
Injector Location
Aeration
Shutter
Tell the user of the location of the gas isolation cock for use in
an emergency .
Leave this Manual with the user or purchaser .
nipple located downstream of the gas tap .
clockwise to reduce or counter-clockwise to increase
pressure . Set pressure to correspond with Table E .
Test Point
Pilot
Adjuster
Low Flame
Adjuster
Part # 4521357 (12/07)

Advertisement

Table of Contents
loading

This manual is also suitable for:

G24-24gfsdG24-36gfsdG24-48gfsdG24-60gfsdG24-72gfsd

Table of Contents