5.7

Lifting points

Prepare a suitable lifting system using the rings
shown in Fig. 14.
5.8

Boiler fixing

Fig. 15 shows how to apply the burner to a boiler with a head-
piece that is not cooled.
It is recommended that the head protrusion should not exceed
200 mm. However, the refractory wall must not extend beyond
the end of the combustion head of the burner.
mm
DB 12 SM C03
Installation