5. Reconnect the grounding cable by screwing the appropriate M5 screw from the inside
of the panel (Fig. 5.8). Close the cover panel by screwing the 4x M5 screws
Fig. 5.8
Work on the back of the rack for DC connections.
6. Inside the rack are available DC power cables (A, Fig. 5.11) identifi ed by black
cable (negative) and orange cable (positive) to be connected to the zeroCO
- BESS 125K. The eyelet terminals (B, Fig. 5.11) They are factory connected to
disconnectors.
7. Pass the DC power cables inside the slot at the base (Fig. 5.12) and, proceeding
from above, let the two quick connector terminals come out.
8. Connect the black quick connector terminal to the D- connector on the BMS (A, Fig.
5.13) of zeroCO
9. Connect the orange quick connector terminal to the D+ connector on the BMS (B,
Fig. 5.13) of zeroCO
48 - Installation
- BESS 125K.
2
- BESS 125K.
2
Fig. 5.9
.
BMS
2