Preparing the server
Preparing the
server for operation
Procedure
Procedure
1. Install any options or cables previously removed to access the TPM connector.
2. If removed, install the air baffle .
3. Install the access panel .
4. Install the front bezel .
5. Do one of the following:
If the server is in tower mode: Position the tower server for operation .
If the server is in rack mode: Install the server on the tray .
6. Connect all peripheral cables to the server.
7. Connect the power cords:
a. Connect each power cord to the server.
b. Connect each power cord to the power source.
8. Power up the server .
The installation is complete.
for operation
Preparing the server for operation
149