COMMISSIONING THE
ROSEMOUNT 3051N
WITH A HART-BASED
COMMUNICATOR
2-4
NOTE
Security jumper not installed = Not Write Protected.
Alarm jumper not installed = High Alarm.
Commissioning consists of testing the transmitter and verifying transmitter
configuration data. You may commission Rosemount 3051N transmitters
either before or after installation. Commissioning the transmitter on the bench
before installation using a HART-based Communicator ensures that all
transmitter components are in good working order and acquaints you with the
operation of the device.
00809-0100-4808, Rev CA