5. Installation
11. Install 10 battery packs in the next layer (L3-A, group 3 positive string). Be sure to keep terminal sides of all batteries up
(Figure 5-10A).
12. Install another 10 battery packs to the layer (L3-B, group 3 negative string). Be sure to keep terminal sides of all batteries
up (Figure 5-10B).
13. Reinstall the right side and left side bracket bars of group 3 batteries (Figures 5-11A and 5-11B).
Figure 5-10A
Figure 5-11A
27
Figure 5-10B
Figure 5-11B