4.3

Preparing the base area

In order to secure the charging station securely on the intended base area, you need to prepare the base area.
Example of foundation
Make a static calculation for the base area to ensure stability. This calculation must include the following factors, among
others:
• Ground survey
• Wind load
• Snow load
• Earthquakes
The dimensions and design of the foundation are determined by the static calculation. The figure below shows a schematic
example of the design of the foundation made of reinforced concrete. The cable routing serves only as an example. Plan cable
routing in accordance with the local conditions. The dimensions for the area of cable laying are specified in mm in the figure.
Base area of charging station
a
Reinforced concrete
s
Area for the cable routing
d
Cable inlet and cable outlet
f
Figure 4-5
Example of foundation