Section 5 - Commissioning; Preparation; Preparation - General; Inspection - York YCAV0569 Installation Operation & Maintenance

Air-cooled screw liquid chillers
Table of Contents

Advertisement

COMMISSIONING

PREPARATION

Commissioning of this unit should only
be carried out by YORK Authorized
personnel.
Commissioning personnel should be thoroughly familiar
with the information contained in this literature, in ad-
dition to this section.
Perform the commissioning using the detailed checks
outlined in the EQUIPMENT START-UP CHECK
SHEET on Page 120 as the commissioning procedure
is carried out.
PREPARATION – GENERAL
The following basic checks should be made with the
customer power to the unit switched OFF.
Proper electrical lock out and tag out
procedures must be followed.

Inspection

Inspect unit for installation damage. If found, take action
and/or repair as appropriate.

Refrigerant Charge

Packaged units are normally shipped as standard with a
full refrigerant operating charge. Check that refrigerant
pressure is present in both systems and that no leaks are
apparent. If no pressure is present, a leak test must be
undertaken, the leak(s) located and repaired. Remote
systems and units are supplied with a nitrogen hold-
ing charge. These systems must be evacuated with a
suitable vacuum pump/recovery unit as appropriate to
below 500 microns.
Do not liquid charge with static water in the cooler.
Care must also be taken to liquid charge slowly to avoid
excessive thermal stress at the charging point. Once the
vacuum is broken, charge into the condenser coils with
the full operating charge as given in the Technical Data
Section.
36
COMMISSIONING

Service and Oil Line Valves

Open each compressor suction, economizer, and dis-
charge service valve. If valves are of the back-seat type,
open them fully (counterclockwise) then close one turn
of the stem to ensure operating pressure is fed to pressure
transducers. Open the liquid line service valve and oil
return line ball valve fully in each system.

Compressor Oil

To add oil to a circuit - connect a YORK hand oil pump
(Part No. 470-10654-000) to the 1/4" oil charging valve
on the oil separator piping with a length of clean hose
or copper line, but do not tighten the flare nut. Using
clean oil of the correct type ("L" oil), pump oil until
all air has been purged from the hose then tighten the
nut. Stroke the oil pump to add oil to the oil system.
The oil level should be between the middle of the lower
and middle of the upper sight glasses of the oil separa-
tor. Approximately 4-5 gallons is present in the each
refrigerant system, with typically 1-2 gallons in each oil
separator. Oil levels in the oil separators above the top
sight glass in either oil separator should be avoided and
may cause excessive oil carryover in the system. High
oil concentration in the system may cause nuisance trips
resulting from incorrect readings on the level sensor and
temperature sensors. Temperature sensor errors may
result in poor liquid control and resultant liquid overfeed
and subsequent damage to the compressor.

Fans

Check that all fans are free to rotate and are not dam-
aged. Ensure blades are at the same height when rotated.
Ensure fan guards are securely fixed.

Isolation / Protection

Verify all sources of electrical supply to the unit are
taken from a single point of isolation. Check that the
maximum recommended fuse sizes given in the Techni-
cal Data Section has not been exceeded.

Control Panel

Check the panel to see that it is free of foreign materials
(wire, metal chips, etc.) and clean out if required.
FORM 201.21-NM2 (616)
JOHNSON CONTROLS

Advertisement

Table of Contents
loading

Table of Contents