Condensor & Fan Rotation; General Operation - York YCAV0569 Installation Operation & Maintenance

Air-cooled screw liquid chillers
Table of Contents

Advertisement

FORM 201.21-NM2 (616)

General Operation

After completion of the above checks for System 1,
switch OFF the 'SYS 1' switch on the keypad and repeat
the process for each subsequent system. When all run
correctly, stop the unit, switch all applicable switches
to the 'ON' position and restart the unit.
Assure all checks are completed in the EQUIPMENT
START-UP CHECK SHEET (Pages 120-125). The
chiller is then ready to be placed into operation.
5