4.2.3.

The completeness and transport damage

4.2.4.
Transport to the installation place (switchgear room)
Removing the transport units from the wooden palettes
28
Fig11. Unloading by crane
Unload the transport units and set them down as close to the switchgear building as
possible in order to avoid unnecessary ways.
Move the transport units into the building, if possible on their wooden pallets. Only
remove packing where absolutely necessary in order to keep the switchgear as clean
as possible.
Remove foil only in the building, right before assembling the transport units.
Check whether the delivery is complete and correct using the delivery note and
packing lists
Compare the serial number of the switchgear panels on the delivery note with that on
the packing and the rating plates of the panels
Check whether the accessories are complete
Temporarily open the packing in a weatherproof place, preferably in the building
Immediately determine and record any damage (and the cause thereof if possible). In
case of transport damage, do this together with the forwarding agent
Repair transport damage or have it repaired, otherwise you may not start installation
Check whether the delivery is complete using the delivery note and packing lists. If the
delivery is incomplete, inform the regional SIEMENS representative
Repack the switchgear as far as possible and reasonable. Do not remove the PE foil
until reaching the mounting position in order to keep the switchgear as clean as
possible
Thoroughly clean the switchgear room, since extreme cleanliness is required during
installation.
Move the transport units on their wooden pallets as far as possible.
Move the transport units to the switchgear room in the order of installation.
Inside the building, move the transport units to the place of installation using a lifting
truck, fork-lift truck or rollers.
Set down the transport units in the correct sequence directly in front of the place of
T
h
installation. Leave enough clearance between the transport units to perform
installation work.
DANGER!
Non-observence of the weight loads of the panels can endanger people or damage the
transport units while unloading.
Please ensure that the lifting gear used meets the requirements of the weight loads
of the panels from the table (see page22, "Transport weights and dimensions with
packing") as a minimum.