Fig72. Operation directions of two levers to disconnect
the withdrawable VT
Fig74. Dismounting L2 phase voltage transformer
Power cable
installation
881-4027.9 * INSTALLATION AND OPERATING INSTRUCTIONS 8BT2 * Revision 04
Remove 18pcs M10 bolts from the rear cover (fig70).
Remove the rear cover.
Take out L2 phase voltage transformer (fig74).
Insert again two operating layers into the hole as done in fig72.
Move two operating levers (pos.nr.
to open the shutter just behind the voltage transformers
Now, it is possible to reach the cable compartment (fig75).
Check contact surfaces of cable terminations, brush if necessary and apply a thin film
of Vaseline.
Slip rubber sleeve for the metal floor plates over the cable.
Mount cable termination according to the manufacturer's instructions.
Pull cable into connection compartment.
Connect cable at the panel connection.
ATTENTION!
The cable compartment can be destroyed if cable terminations with inadequate
dimensions are used.
Use only cable terminations with the dimensions hereafter.
Depending on the manufacturer of the cable terminations, the dimensions may
differ from those described in here. Please make sure that dimensions do not
exceed the limit values.
Fig73. Rear view of withdrawable VTs
Fig75. Rear access to the cable compartment
in fig71) downward at the same time to be able