This section provides instructions on how to unpack and move the equipment into place. Also,
LCN cable lengths and routing considerations are presented.

3.1 EQUIPMENT UNPACKING

Following factory assembly, inspection, and test, the configured cabinets and consoles are
protectively wrapped for domestic shipment, or wrapped and crated for overseas shipment.
The LCN equipment cabinets are strapped to a wooden shipping skid or pallet that is
blocked on all sides. The Universal Station (US), Universal Station X , and Global User
Station are bolted to a shipping skid and wrapped or crated in a similar manner as the
cabinets. The USs can be optionally equipped with castors or leveler glides. Castors are
available for use after the skid is removed.
All intracabinet/console cables and table-top printers are boxed separately.
STATICIDE work area before unpacking equipment. Use antistatic spray on floors, chairs,
workbench, mats, tools, etc., in the work area. This inhibits static generation that can damage
electronic equipment, see Section 6.
Upon arrival at the system site, remove shipping crate and protective wrapping and
carefully inspect the equipment for any physical damage. If damaged, immediately notify
the carrier and your Honeywell sales representative as to extent and type of damage. Also
check each piece of equipment against the invoice list for any missing items.

3.2 EQUIPMENT PLACEMENT

The cabinets and consoles can be carefully moved into position, by use of lift trucks or
mobile lifters. The Universal Stations can be rolled on their casters. Position the
equipment according to the system-layout plan (refer to LCN Site Planning manual or
System Site Planning manual). Verify that door openings allow access to LCN modules
and controller card files for maintenance and checkout.
The shipping skid can be removed from the cabinet by first removing the wooden block on
one side of the skid and gently sliding the cabinet off of the skid and onto the floor. Do not
tilt the cabinet beyond 45° as this may cause damage to the doors and side skins. To
remove the skid from the Universal Station, unbolt the wooden cleats that span the
bottom-entry cutouts and slide the Universal Station off the skid as with the cabinet.
Do not lift Operator Interface Stations by the keyboard tray.
LCN System Installation

EQUIPMENT UNPACKING AND PLACEMENT

NOTE
W A R N I N G
3-1
3
Section 3
9/96

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents