All packing materials and restraints have been removed from each cabinet.
-
Each cabinet in the Parallel Capacity/Redundant system is placed in its installed
-
location.
A ground bond is installed between any cabinets that are bolted together.
-
All switchboards, conduits, and cables are properly routed to the SSBM, UPMs and
-
auxiliary cabinets.
All power cables are properly terminated.
-
A ground conductor is properly installed.
-
If neutral connection is used, no other N---G bonds exist downstream from the UPMs.
-
Battery cables and harness are terminated on E4 and E5.
-
Internal battery cabinet connections have been completed (bus bars, plugs, etc.).
-
Shunt trip signal wiring is connected from UPMs to battery breaker(s).
-
Air conditioning equipment is installed and operating correctly.
-
The area around the installed Parallel Capacity/Redundant system is clean and
-
dust-free. (It is recommended that the Parallel Capacity/Redundant system be
installed on a sealed concrete pad or a sealed concrete floor.)
Adequate work space exists around the SSBM, UPMs and other cabinets.
-
Adequate lighting is provided around the Parallel Capacity/Redundant system.
-
A 120VAC service outlet is located within 25 feet of the Parallel Capacity/Redundant
-
system.
All circuit breaker trip units settings have been completed per the user's coordination
-
study.
Each Remote Monitor Panel (RMP) is mounted in its installed location. (OPTIONAL)
-
The control wiring for each RMP is terminated inside the UPS cabinet. (OPTIONAL)
-
The Remote Emergency Power Off (EPO) device is mounted in its installed location
-
and its wiring terminated inside the SSBM. (OPTIONAL)
Summary alarms and/or building alarms are wired appropriately. (OPTIONAL)
-
A Relay Interface Module (RIM) is mounted in its installed location and its wiring is
-
terminated inside the SSBM. (OPTIONAL)
A remote battery disconnect control is mounted in its installed location and its wiring is
-
terminated inside the UPS and battery cabinet. (OPTIONAL)
Startup and operational checks performed by authorized service personnel.
-