Commissioning, inspection, maintenance
Further details regarding the individual steps
15. "ON"
to carry out the relay
test for the selected
function or connected
components.
Note
Only switch on com-
pressor and instanta-
neous heating water
heater when secondary
pumps are running. If
the secondary pumps
are not running, the
compressor and instan-
taneous heating water
heater (accessory) are
switched off by the
safety equipment.
16. "OFF"
to terminate the relay
test for individual func-
tions or connected
components.
or
17. "RESET"
to terminate the relay
test for all functions and
connected components
together.
"Commissioning" menu
Programming
Heating circuit 1
126
18. "BACK"
19. y/x for the required mixer
20. "OPEN", "CLOSE", "STOP" to
21. "BACK"
22. For the contents of the "Commis-
23. "BACK"
24. Note
Aim
To set all required
parameters according
to the system configu-
ration, see page 169
and operating instruc-
tions.
Venting
(cont.)
for "Mixer"
(e.g. "Heating circ. 2",
"Ext. heat source",
etc.).
open, close or stop the mixer.
for "Commissioning"
sioning" menu, see the following
table.
twice to end commis-
sioning. The system is
operational.
Messages are displayed by man-
ually controlling some components
during commissioning. These do not
indicate appliance faults.
Acknowledge all messages (see
page 132).
System characteristics
___
Secondary pump and heating