2. BitStorm 1900 Installation and Testing
Task 008: Installing Voice/Data & Filter Shelf
Connections
2-58
Use this procedure to connect the BitStorm 1900 to the EtherLoop
cross-connect in voice/data applications.
Requirements
This procedure requires the following tools and materials:
10 BitStorm 1900 cable harnesses
10 intermediate cables
10 BitStorm 1900 data cables
"Appendix B. Cabling Specifications," on page 115 contains the
specifications for the cables and wiring required in this procedure.
Step
Procedure
1.)
Place and secure the dedicated EtherLoop cross-connect on the
facility main distribution frame.
2.)
Designate and label one side of each block as "Line/CPE," and the
other side as "Voice."
3.)
Review pin and pair assignments in Figure 2-2, "Pin and Pair
Assignments for the Champ to Omni Grid Cable (Part #: 04-00007-
10)," on page 59.