Commissioning using a BOP-2 operator panel

Plug Basic Operator Panel BOP-2 into the inverter
Procedure
To plug Basic Operator Panel BOP-2 onto the inverter,
proceed as follows:
1. Remove the blanking cover of the inverter.
2. Locate the lower edge of the BOP-2 housing in the
matching recess of the inverter housing.
3. Press the BOP-2 onto the inverter until you hear the
latching mechanism on the inverter housing engage.
You have plugged the BOP-2 onto the inverter
When you power up the inverter, the BOP-2 will be ready for
operation.
5.3.1

Starting basic commissioning

Carry out basic commissioning
Preconditions
Procedure
Proceed as follows to carry out basic commissioning:
1.
2.
3.
4.
5.
SINAMICS G120C converter
Operating Instructions, 07/2015, FW V4.7 SP3, A5E34263257B AC
• The power supply is switched on.
• The operator panel displays setpoints and actual values.
Press the ESC key.
Press one of the arrow keys until the BOP-2 displays the "SETUP" menu.
In the "SETUP" menu, press the OK key to start basic commissioning.
If you wish to restore all of the parameters to the factory setting before
the basic commissioning:
4.1.
Switch over the display using an arrow key: nO → YES
4.2.
Press the OK key.
When selecting an application class, the inverter assigns the motor
control with the appropriate default settings:
STANDARD → Standard Drive Control (Page 95)
DYNAMIC
EXPERT
5.3 Commissioning using a BOP-2 operator panel
→ Dynamic Drive Control (Page 97)
→ Basic commissioning for experts (Page 101)