Commissioning

4.2 Commissioning with BOP-2 operator panel

If you intend to commission the converter with IOP operator panel
The IOP offers commissioning wizards and help texts for an intuitive commissioning. For
further information refer to the IOP operating instructions.
If you intend to commission the converter with PC tools STARTER and Startdrive
Overviev of the most important steps with STARTER:
1. Connect the PC to the converter via USB and start the PC tool.
2. Choose the project wizard (menu "Project / New with assistent").
– In the project wizard choose "Find drive units online".
– Select USB as interface (Access point of the application: "DEVICE ...", interface
– Finish the project wizard.
3. STARTER has now created your project and inserted a new drive.
– Select the drive in your project and go online
– In your drive open the "Configuration" mask (double click).
– Start commissioning with the "Assistent" button.
For further information refer to converter operating instructions.
4.2
Commissioning with BOP-2 operator panel
Plug Basic Operator Panel BOP-2 into the inverter
Procedure
To plug Basic Operator Panel BOP-2 onto the inverter,
proceed as follows:
1. Remove the blanking cover of the inverter.
2. Locate the lower edge of the BOP-2 housing in the
matching recess of the inverter housing.
3. Press the BOP-2 onto the inverter until you hear the
latching mechanism on the inverter housing engage.
You have plugged the BOP-2 onto the inverter
When you power up the inverter, the BOP-2 will be ready for
operation.
42
parameter assignment used: "S7USB").
Overview of the manuals (Page 86)
.
Compact Operating Instructions, 11/2016, FW V4.7 SP6, A5E39339884B AA
SINAMICS G120C, FSD ... FSF inverters

Advertisement

Table of Contents
loading

Table of Contents